Signed and put into production! At the end of the year and the beginning of the year, China Power Construction's pumped hydro energy storage ran out of "acceleration"
Release time:2024-08-29click:9
Recently, PowerChina’s pumped storage energy sector has sent a new year gift package. A large number of pumped storage power stations have signed contracts, started construction, and put into operation. The industry situation is very gratifying!
The first batch of units of Shandong Wendeng Pumped Storage Power Station was put into operation for power generation
1, 2023 On March 1, Units 1 and 2 of Shandong Wendeng Pumped Storage Power Station, which was surveyed and designed by the Beijing Institute of Power Construction Corporation of China and constructed by the First, Fourth and Fifth Hydropower Bureaus, were officially put into operation for power generation.
The power station is located in Jieshi Town, Wendeng District, Weihai City, Shandong Province, with a total installed capacity of 1.8 million kilowatts and a designed annual power generation of 2.7 billion kilowatt hours.
As the pumped-storage power station with the largest installed capacity in Shandong Province, the Wendeng pumped-storage power station will give full play to its functions of peak shaving, energy storage, and power output, and will contribute to the safety of Shandong power grid. Operation and reliable power supply provide stronger guarantee.
Guizhou Guiyang Pumped Storage Power Station was approved to start construction
On December 30, Guiyang Institute of Power Construction of China Guizhou Guiyang Pumped Storage Power Station, a key project for the implementation of the "14th Five-Year Plan" in Guizhou Province that was surveyed and designed, was approved by the Guizhou Provincial Development and Reform Commission, becoming the first pumped storage power station in Guizhou Province to complete the approval, marking the start of the project Entering a new stage of project construction.
The power station is located in Gubao Town, Xiuwen County, Guiyang City. It is located in the load center of Guizhou Power Grid in central Guizhou. It has a total installed capacity of 1.5 million kilowatts and is responsible for peak shaving, valley filling, and storage of Guizhou’s power system. energy, frequency modulation, phase modulation and emergency backup tasks.
After the project is completed, it will improve clean energy consumption capacity, realize a multi-energy complementary energy structure, ensure the safe operation of Guizhou's power grid, and provide power guarantee for Guizhou's high-quality development.
The construction of the pumped storage power station in Song County, Henan Province started
On December 29, the country’s “14th Five-Year Plan” pumped water One of the key implementation projects of energy storage planning, Henan Songxian Pumped Storage Power Station held a groundbreaking ceremony.
The power station is located in Checun Town, Song County, Luoyang City, Henan Province. The Zhongnan Institute of Power Construction Corporation of China is responsible for the survey and design, with a total installed capacity of 1.8 million kilowatts.
After the project is completed and put into operation, it will significantly improve the peak shaving, valley filling, frequency and phase modulation and emergency backup capabilities of the central China and Henan power grids. It will ensure the energy and power security in the region, optimize the system power supply structure, and improve the utilization rate of clean energy. It is of great significance to promote clean and low-carbon energy transformation.
Won the bid for Zhejiang Yongjia Pumped Storage Power Station
Recently, China Power Construction Engineering Corporation’s East China Institute won the bid for Zhejiang Yongjia Pumped Storage Power Station Power station design, procurement and construction EPC general contracting project.
Yongjia Pumped Storage Power Station is one of the national pumped storage medium and long-term development planning projects. The power station has a total installed capacity of 1.2 million kilowatts. It is located in Yongjia County, Wenzhou City, Zhejiang Province. It is a "nuclear power station" built by Wenzhou. A landmark project in the whole chain of "scenery, water, hydrogen storage". After completion, it will mainly undertake the tasks of peak regulation, valley filling, energy storage, frequency regulation, phase regulation and emergency backup of Zhejiang Power Grid, and at the same time effectively promote the development of red tourism, research and other mutual wealth industries.
Construction of Qinghai Tongde Pumped Storage Power Station started
On December 28, Qinghai Tongde Pumped Storage Power Station The preliminary bid has fully entered the construction stage.
The power station is located in Hebei Township, Tongde County, Hainan Prefecture, Qinghai Province. It was surveyed and designed by the Northwest Institute of Power China and constructed by the Third Hydropower Bureau. The project area is far away from the full-stage survey and design of Power China. The main construction task of the Mar dam hydropower station is about 11 kilometers.
The power station is a daily adjustable hybrid pumped storage power station with a total installed capacity of 2.4 million kilowatts. After completion, it will undertake tasks such as energy storage, peak shaving and valley filling, and emergency backup for the Qinghai power grid. .
Hebei Xingtai Pumped Storage Power Station started construction
On December 27, it was surveyed by the Beijing Institute of China Power Construction The groundbreaking ceremony was held for the Hebei Xingtai pumped storage power station designed.
The power station is located in Xindu District, Xingtai City. It is a key implementation project of the country’s “14th Five-Year Plan” with a total installed capacity of 1.2 million kilowatts.
After the project is completed, it will undertake the peak shaving, valley filling, energy storage, frequency modulation, phase modulation, emergency backup and other tasks of the Hebei power grid power system. At the same time, it is of great significance to stimulating the local economy, promoting employment, improving people's livelihood, and accelerating green transformation and development.
Hubei Songzi Pumped Storage Power Station started construction
On December 26, it is one of the key implementation projects of the national “14th Five-Year Plan” pumped storage plan. Hubei Songzi Pumped Storage Power Station held a groundbreaking ceremony, marking that the project has entered the construction and implementation stage.
The power station is located in Jingzhou City, Hubei Province. The Zhongnan Institute of Power Construction Corporation of China is responsible for the survey and design work, with a total installed capacity of 1.2 million kilowatts.
After completion, it will be of great significance for optimizing energy resource allocation and power supply structure in Hubei Province, effectively alleviate the prominent peak load regulation contradiction of the western Hubei power grid, and strongly support the safe and stable operation of the power grid.
Construction of Hubei Pankou Pumped Storage Power Station started
On December 24, Hubei Pankou Pumped Storage Power Station A groundbreaking ceremony was held. The Fifth Hydropower Bureau of China Power Construction Corporation Limited participated in the ceremony as the construction unit.
Hubei Pankou Pumped Storage Power Station is one of the national pumped storage medium and long-term development planning projects, with a total installed capacity of 300,000 kilowatts. The power station uses the reservoir of the existing Pankou Hydropower Station as the upper reservoir and the reservoir of the Xiaoxuan Hydropower Station as the lower reservoir. After completion, the annual power generation is expected to be 350 million kilowatt hours.
This project is a hydroelectric cascade integration transformation project, which has good benefits in improving the power generation efficiency of conventional hydropower stations, power grid peak regulation, emergency backup, and energy conservation and emission reduction.